468-unit high-rise

This 3-phase condominium in Montreal prepared its parking spaces for electric vehicle charging by installing RVE technology. The installation was carried out by Lilco Électrique.

Technical Specifications

Type of construction

existing building (retrofit)

Type of occupancy

condo

Building size

301 units or more

Number of floors

11 to 20

Number of parking spaces

301 or more

Location of electricity meters

accessible from the parking spaces

Location of parking spaces

indoor, covered

Type of parking spaces

assigned

Products used

Challenge

Powering an electric vehicle charging infrastructure in a multi-unit building where the electric meters are located in the garage basement (accessible).

Solution

Using a homogenous solution was possible to power charging infrastructure between the 468 units of this condo building and for the EV chargers that were requested to be installed. Indeed, all meters are accessible and the condo association wanted a solution according to a user-pays principle, thus allowing the use of DCCs everywhere. A total of 74 DCCs have been installed, and a charging policy has been put in place to standardize the installations:

  • DCC-9 for units with an electrical panel of 125A and less in need of a charger now
DCC-9
DCC-9
DCC-9
DCC-9